Specifications consist of database items which define which type of pipe, fittings, valves, hangers, etc., will be used in a piping system.

Image Modified The Specification section will take approximately 2 hours.

Table of Contents
styledecimal
printablefalse

Exercise 14: Copying Specs

  1. Go to the Job where you want the new Spec copied to and click on the Specs tab.
    Image Modified
  2. Click Image Modified.
    Image Modified
  3. Select the Templates Folder, the Heating & Cooling Job, and then the Spec you want to copy into your current Job. When you select Image Modified, the spec is copied into your current job.

Next, you will manipulate the specification to use the exact specifications your company will use on a daily basis. This includes setting up the type of Pipe, Fittings, Joints, Valves, Flanges, Hanger Types, Hanger Spacing, Insulation Thickness, Specialties Items and Bookmarks.

Exercise 15: Change the Size Ranges to Be Used in a Spec

  1. Click on the white box in a row. The box changes from white to gray.
  2. To select multiple sizes, click and hold your mouse down on the white box and drag the cursor to the right. Release the mouse button and the sizes will be selected.

Exercise 16: Edit the Material Type in a Spec

The dots only appear on single items: pipe, valves, etc. On fittings, there are many items represented and they may have different sizes possible.

Image Modified

  1. To open and change a spec, highlight and double click on the spec.
  2. The Spec screen lets you select the Group, Class, Joint Group, Joint Class, and Joint Length. This breakdown is important for rapid lookup.
    Image Modified
    Group: Type of material.
    Class: Weight or number of how it is broken down.
    Joint Group and Joint Class: Select the Joint Group and Joint Class for automatic generation of joint quantities. Note that you should always select a coupling for types of pipe that require couplings. Any solder or other pipe joint material will be added automatically with the coupling. In some classes of pipe, Joint Groups, Classes or both may be automatically selected by default.
    Joint Length: Tells the system how often the joints for the pipe will be automatically counted.
  3. Ones you have the selection, click Image Modified. The main spec screen reappears

Exercise 17: Edit the Fittings in a Spec

Change the fittings so they are accurate for our Job.

  1. Double click on a Fitting.
    Image Modified
  2. The Fitting Spec screen appears. You can now verify that the selection is correct.
    Image Modified
  3. Click Image Modified to return to the Spec screen.

Exercise 18: Edit the Valves in a Spec

Change the Valves so they are accurate for our Job.

Image Modified

  1. Double click on a Valve.
  2. The Valve Spec screen appears. You can now verify that the selection is correct. If any accessories are needed, they can be selected here by clicking on the accessory to highlight it. You can select as many accessories as you want.
    Image Modified
    Note: For industrial contractors, you may want to select QUOTED valves since you may only be interested in getting the labor for the item.
  3. Click Image Modified to return to the Spec screen.

To see more items on this Spec screen, click the down arrow on the bottom right side of the screen. The screen scrolls down.

Image Modified

Exercise 19: Edit the Flanges in a Spec

Change the Flanges so they are accurate for our Job.

  1. Double click on a Flange.
    Image Modified
  2. You can now verify that the selection is correct. Bolt sets and gaskets are also selected here for automatic takeoff with each flange. Click Image Modified to return to the Spec screen.

Exercise 20: Edit the Hangers in a Spec

Change all the Hanger components so they are accurate for our Job.

Keep in mind you can have up to 7 hangers per Specification (including Riser Clamps). In addition, the hanger that is first (at the top) of the “Hanger” section in the spec will be the default hanger that shows up in the Takeoff screen. If the job is an all concrete job, you may want to move that to the top using the Shift Command. This will eliminate extra clicking when you get to Takeoff.

Notice as you scroll down the specification screen, you can see the variety of hangers that are available.

Image Modified

Double click on a hanger. You can now verify that the selection is correct. All of the components shown will be calculated for each hanger of this type that is being used in Takeoff.

Image Modified

Notice the dot next to “Insulation Size” is selected. This means the hanger is sized to include the pipe diameter plus insulation thickness (x2). If Pipe Size is selected, the hanger is sized to only pipe diameter (no insulation).

Verify that the insulation thickness is correct so that the hanger size and sleeves are calculated correctly. (This is required for the proper over sizing of hangers.) Click Image Modified to return to the Spec screen.

Adding a Hanger (for Excavation)

You can add a new hanger.

  1. Go to the specification where you would like to add the hanger.
  2. Click Image Modified.
    Image Modified
  3. A pull down list appears.
    Image Modified
  4. Click on Hanger/Excav. A screen appears with Hanger/Excavation Forms where you can select which hanger you would like to add.
    Image Modified

    NOTE: Click on Image Added 
    for your underground pipe.
  5. Complete the hanger form as necessary.
    Image Added

Exercise 21: Edit the Hanger Spacing in a Spec

Scroll down to view more items. Look at the Hanger Spacing along the left-hand column.

Image Added

NOTE: If hanger spacing is not selected for a specific size range, then the system cannot calculate hangers automatically.

Exercise 22: Changing the Insulation Thickness in a Spec

Change the insulation thickness so it is accurate for your Job.

Notice on the following screen that the 1″ Insulation is specified from ¼” up to 1½” pipe diameter. (This is shown by the gray boxes.)

  1. Double click on the Insulation thickness.